MMP Police

Print

1 Project Name Police MMP
2 Project Cost Rs. 12,58,497/- (Agreement Cost)
Rs. 47.546 Crore for five years - DPR Cost
3 DIT Share -
4 State Share -
5 Duration 12 Weeks
6 Release Payment made by Capacity Building A/c as per Letter No 720/ITDA-129
Dt. 17-11-2007
7 Date of Advertisement/
Name of Papers
04-04-2007
Amar Ujala, Dainik Jagran, The Times of India, Hindustan Times, Economic Times

Corrigendum 22-04-07
Amar Ujala, Dainik Jagran, The Times of India, Hindustan Times, Economic Times
8 Detail as RFP RFP No. ITDA/ NeGP - MMP/ Police/ 2008 Dt. 28-02-2008
Send To:
1- M/s SREI New Delhi
2- M/s TCS Lucknow
3- M/s Deloitte New Delhi
4- M/s Wipro Ltd.
5- M/s Price Water House Coopers Pvt. Ltd.,
6-  M/s 3 I Infotech Ltd, New Delhi
7-M/s TCIL New Delhi
8- M/s Ernest & Young Pvt. LTd. Gurgaon
9 Date of Tender RFP agreed on 28-02-08
10 No. of Tender Received/
Name of the Firms
Bids Received from:
1- M/s Price Water House Coopers
2- M/s 3i Infotech Ltd, New Delhi
3- M/s Deloitte Touch Tahmatsu India Pvt. Ltd.
11 Date of Opening of
Tender
26-04-08 (opening of Financial Bids)
12 Selection of
Consultant
M/s 3i Infotech Ltd.
13 Bid Value Rs. 12,58,497/-
14 Agreement with
Consultant
M/s 3i Infotech Ltd.
15 Duration of
Agreement
12 Weeks
16 Mile Stone of
Agreement
1-  Advance against BG valid for 6 months (20%)
2-  Submission of the "Scope and AS-IS assment report" finalised after the First Departmental Workshop and its approval (15%)
3-  Submission of the "Report of GPR and TO-BE process Maps" finalised after the second departmental workshop and its approval (20%)
4-  Submission of the Detailed Project (DPR) (20%)
5-  Acceptance by Govt. of Uttarakhand (10%)
6- Acceptance by GOvt. of India/ Funding Agency (15%)
17 Completed Mile Stone 1-  Advance against BG valid for 6 months (20%)
2-  Submission of the "Scope and AS-IS assment report" finalised after the First Departmental Workshop and its approval (15%)
3-  Submission of the "Report of GPR and TO-BE process Maps" finalised after the second departmental workshop and its approval (20%)
4-  Submission of the Detailed Project (DPR) (20%)
18 Payment to Consultant Rs. 9,43,892/-
19 Pending Bill/
Liabilities of Consultant
-
20 Meeting regarding project, Agenda & Minutes in Chronological Orders 10-07-09
26-04-08
21 Present Status Forwarded to GoI
22 Action Needed Funding by GoI
23 Remark  
देवभूमि जनसेवा केंद्र
Devbhoomi Janseva Kendra
Toll free No. 1800-3000-2300
(Queries/complaints regarding CSCs and E-district services)

NeGP Projects

  • About NeGP
  • SSDG
  • CSC
  • SDC
  • SWAN
  • e District
  • Mission Mode Projects
  • read more...